San Dieguito Pump Station Replacement Project

San Dieguito, CA 2015-2017 Replacement (demolition) of an existing water pumping station with a new 15 MGD pumping station (expandable to approximately 20 MGD), including replacement of the existing pump station intake. Install electrical equipment including vertical turbine pumps, VFDs,…

Otay 870-2 Pump Station Replacement

Otay Mesa, CA 2017-2020 Construction of a potable water pump station, 66” & smaller yard piping, 37 MG reservoir floating cover and liner replacement, reservoir recirculation system, existing access road improvements, utility connections, and all other work and appurtenances.

Escondido – Vista WTP Disinfection & Electrical System Upgrades

Escondido, CA 2014 – 2017 Installation of a new on-site sodium hypochlorite generation (OSG) system to replace the existing gaseous chlorine system for disinfection, installation of a new chlorine dioxide generation system to replace the existing system, and upgrades to…

Dry-Year Yield Well Project

Ontario, CA 2010 The Dry-Year Yield Wells Water Treatment Plant project was completed in March 2010, with a total value of construction of $7,885,110. This project includes the construction of 2 well sites, block building, pipeline work, paving, sodium hypochloride…

Alhambra Groundwater Treatment Plant

Alhambra, CA 2008 The Alhambra Groundwater Treatment Plant project was completed in September 2008, with a total value of construction of $9,010,045. This project includes the construction of an ion exchange system, GAC filters, backwash tanks, chemical feed, filter bags,…

Crafton Hills and Citrus Pump Stations

Mentone, CA 2014 The Crafton Hills and Citrus Pump Stations project has a total value of construction worth $27 million. This project includes a new 3.0-million-gallon concrete reservoir, pipelines with up to 66” diameter, electrical work, paving, earthwork and shoring….

Greer Ranch Lift Station